A total expenditure of Rs 4.10 lakh crore has been made under Bharatmala Pariyojana Phase I as on Oct. 31, 2023, and the difference in actual project cost and normative cost is due to increase in cost of raw material and land acquisition, Parliament was informed on Wednesday.
In a written reply to a question in the Rajya Sabha, Union Road Transport and Highways Minister Nitin Gadkari said Comptroller and Auditor General has made observation about the increase in cost of Phase I of the pariyojana.
-
Indian Markets Turning Corner After Two Tough Years, Says Sandeep Tandon -
NDTV Profit Ignite 2026: Experts See Opportunity In Equities, Stay Bullish For Long-Term -
Buy Right, Sit Tight Does Not Work for Individual Stocks, Says Dinshaw Irani -
'Worst Is Behind': Quant MF Sees Market Bottom, Flags 'Extreme Euphoria' In Midcaps -
India's Mutual Fund Industry Could Become A $1 Trillion Opportunity, Say Fund Managers -
'Foreign Investors Are Baraatis': Raamdeo Agrawal's Take On LTCG Tax -
Stay Invested Through Market Cycles: Raamdeo Agrawal at NDTV Profit Ignite -
Ramesh Damani Remains Bullish On India For Next 20-30 Years, Sees Bargains Amid Market Weakness -
CAS Came After A Long Consultation Process: SEBI Chairman Tuhin Kanta Pandey AT NDTV PROFIT IGNITE -
Aim To Cut FPI Onboarding Time From Mth To Five Days: SEBI Chairman Tuhin Kanta Pandey AT NDTV PROFI
"As on October 31, 2023, the total expenditure (BPP-I) is about Rs 4.10 lakh crore...There has been no diversion of funds from other schemes in the execution of BPP-I," he said.
Also Read | Layoffs Are Rising In Tech, But These Skills Are Helping People Unlock Better Pay
According to Gadkari, certain BPP-I projects were earlier planned under other schemes of Ministry of Road Transport and Highways viz, externally aided project, National Highways Original works NH(O), and SARDP scheme, which were subsequently prioritized under BPP-I as per the network planning.
"The difference in actual project cost and normative cost under Bharatmala Pariyojana is due to increase in cost of raw material, increased land acquisition cost, construction of high-speed corridors and increase in GST rates etc," he said.
In 2017, the Cabinet Committee on Economic Affairs approved BPP-I entailing development of 34,800 km of National Highway corridors with total outlay of Rs 5.35 lakh crore.
"This was based on the normative cost and not on the basis of detailed project reports of national highways proposed under Bharatmala Pariyojana."
"DPRs were prepared subsequently and approval of competent authority was obtained for each project," Gadkari said.