Get App
Download App Scanner
Scan to Download
Advertisement
This Article is From Mar 14, 2019

NASA Weighs Shelving Its Own Giant Booster,Β Using Private RocketΒ to Moon

(Bloomberg) -- Additional delays with a Boeing Co. rocket has NASA considering commercial help to mitigate further schedule slips in launching the agency's future deep-space exploration craft.

The Space Launch System β€œis struggling to meet its schedule,” NASA Administrator Jim Bridenstine said at a Senate hearing Wednesday. The rocket won't be ready for a launch in June 2020, when NASA had planned the Exploration Mission-1 flight of its Orion spacecraft around the moon.

The agency is now exploring options for meeting that deadline using β€œcommercial capabilities,” Bridenstine said. He stressed that the agency remains committed to Boeing's SLS, the largest rocket in U.S. history and a β€œcritical capability” for future deep-space missions.

The National Aeronautics and Space Administration will decide how to proceed for an uncrewed test flight as soon as this month, he said.

β€œWe need to consider as an agency all options” to keep the EM-1 mission on schedule, Bridenstine said. β€œNASA has a history of not meeting launch dates and I'm trying to change that.”

Management Flaws

An Oct. 2018 audit by NASA's Inspector General found multiple management flaws in the SLS program, and said that Boeing was likely to spend at least $8.9 billion for the rocket, double the original budget.

A test flight of the Orion capsule was launched in early 2015 aboard a Delta IV rocket built by United Launch Alliance, a joint venture of Boeing and Lockheed Martin Corp.

Without the SLS, NASA would be forced to purchase two heavy-lift vehicle launches and then integrate the Orion with an upper stage in orbit, adding to the cost. Bridenstine told the Senate panel that NASA may need further financial assistance from Congress.

β€œThe integration challenges are significant,” an industry trade group, the Coalition for Deep Space Exploration, said in a statement. The group represents aerospace firms including Boeing and Lockheed Martin. β€œIt is also clear that this approach would require additional funding, since the idea is to undertake both this mission and to continue development of the SLS apace.”

After the hearing, Bridenstine told the industry publication Space News that he hadn't spoken with ULA or Elon Musk's Space Exploration Technologies Corp. about using their heavy-lift vehicles for the EM-1 mission.

A subsequent flight, EM-2, would launch with the SLS in 2023 and carry crew members.

To contact the reporter on this story: Justin Bachman in Dallas at jbachman2@bloomberg.net

To contact the editors responsible for this story: Brendan Case at bcase4@bloomberg.net, Susan Warren

Β©2019 Bloomberg L.P.

Essential Business Intelligence, Continuous LIVE TV, Sharp Market Insights, Practical Personal Finance Advice and Latest Stories β€” On NDTV Profit.

Newsletters

Update Email
to get newsletters straight to your inbox
⚠️ Add your Email ID to receive Newsletters
Note: You will be signed up automatically after adding email

News for You

Set as Trusted Source
on Google Search