Adani Enterprises Q1 Results: Profit At Rs 734 Crore, Margin Expands
The total income of billionaire Gautam Adani-led coal to aviation company was at Rs 21,961 crore.

Adani Enterprises Ltd.'s net profit came in at Rs 734 crore in the first quarter of fiscal year 2026, according to the financial results declared by the ports-to-power conglomerate on Thursday.
The total income of billionaire Gautam Adani-led company was at Rs 21,961 crore.
The firm's profit before exceptional items went up 11.7% to Rs 1,466 crore from Rs 1,313 crore sequentially for the first quarter of financial year 2026.
Adani Enterprises Q1 FY26 Results
Revenue at Rs 21,961 crore.
Ebitda at Rs 3,310 crore.
Margin at 15.1% versus 13.8% (Cons, QoQ)
Profit before exceptional items Up 11.7% At Rs 1,466 crore versus Rs 1,313 crore (Cons, QoQ)
The company's earnings before interest, taxes, depreciation and amortisation from incubating businesses increased by 5% to Rs 2,800 crore on year-on-year basis and contributed 74% to the first quarter fiscal 2026 results, according to the firm's press release.
The firm anticipates operationalisation of the large infra-assets during the current fiscal , which it said would result in "Ebitda unlock and long-term value creation."
The Ebitda from Adani Airports increased by 61% YoY to Rs. 1,094 crore.
"The substantial rise in Ebitda contribution from our incubating businesses reflects strength and scalability of our operating model. This performance has been led by our Airports business, which delivered an exceptional 61% year-on-year growth in Ebitda," Gautam Adani, Chairman of the Adani Group.
"With landmark assets like the Navi Mumbai International Airport, the Copper Plant and the Ganga Expressway set to become operational, we are accelerating our mission to build next-generation infrastructure platforms that are globally benchmarked, technologically advanced and strategically vital to India’s growth story," he added.
Adani Enterprises Business Updates
Adani New Industries
Commissioned India’s first off-grid 5 MW Green Hydrogen pilot plan.
Wind Turbine business received its first external order of 300 MW.
Construction for additional 6 GW module capacity progressing as scheduled.
Adani Connex Pvt. (ACX - Data Center)
Noida data center MEP works in progress.
Hyderabad data center phase II MEP works ~72% completed.
Pune data center phase I works crosses ~85%.
Adani Airport Holdings
Mumbai airport received its tariff order for fourth control period FY25 to fiscal 2029.
Seven new routes and two new airlines added.
Adani Road Transport
Three Hybrid Annuity Model projects are more than ~90% complete.
Ganga Expressway construction crosses ~85%.
Natural Resources – Mining Services
Mine developer and operator agreements signed for Mara II Mahan and Gondbahera Ujheni East coal mine.