Labour Crunch Threatens Cost Overruns, Developers Hope For Festive Boost
India's harsh curbs to contain the pandemic stalled economic activity, leaving millions of low-paid daily wagers out of job. The nation's biggest migration followed as workers set out for their homes hundreds of kilometres away on foot.
One of the biggest sources of employment for them was the real estate sector in Asia's third-largest economy. According to industry lobby Credai-MCHI, about 75% — or 7 lakh of the estimated 9 lakh — on-site real estate workforce migrated to their native states during the lockdown from Mumbai Metropolitan Region alone. That exodus is hurting now. While the government reopened the economy gradually, there aren't enough workers to operate construction sites, causing delays and cost overruns.
Earlier this month, the lobby wrote two separate letters to the Maharashtra government and the Ministry of Railways, seeking help in providing affordable railway transport for workers, primarily from Uttar Pradesh, Bihar, Madhya Pradesh, Jharkhand, West Bengal, and Odisha, to return.
What Developers Fear
It is estimated that the overall project cost may rise 8-10% on account of delay by six-nine months and corresponding shortage in labour and material, according to Amit Goenka, managing director and chief executive officer at Nisus Finance.
“Delays create a huge financial pressure on the project including pressure of lenders, vendors and buyers. It also subdues demand, reduces valuations and creates a significant depression in the project's feasibility,” Goenka said. “Lenders and investors turn cautious to pessimistic in financing and investing in projects that are slow or stuck and have completion risk.”
What Workers Want
According to Rajkumar Jaiswal, president of Maharashtra Building and General Labour Union, the migrants have only two primary demands:
- Payment of their pending wages as many developers are yet to pay them for pre-lockdown work.
- Providing medical insurance in the case that they get infected while working in the city.
“There is a fear in the minds of the people that if they come back, they will be infected. Family members are also not allowing them to return to the city,” said Anand Gupta, a Mumbai-based developer and chairperson of housing and RERA committee of Builders' Association of India. Workers also want free transportation, safety measures, better accommodation, increase in number of toilet blocks, he said.
What Developers Are Offering
Credai-MCHI said it has mandated a number of safety measures at their construction sites to:
- Social distancing to be followed with temperature checks before commencing work.
- Weekly visit by a doctor on site for regular medical check-ups of workers
- Regular fumigation of staircases, lifts, helmets to maximise safety
- Staggered meal times to avoid unnecessary crowding
- Special quarantine facilities for any worker who has tested positive for the new coronavirus or show symptoms.
While developers are ready to bear a one-time cost like bus and air fares to get construction workers back to the city, the success ratio has so far been abysmally low, said Bhavin Thakker, managing director, Mumbai and head, Cross Border Tenant Advisory, Savills India.
Thakker said developers are wary of the higher cost of labour that they may have to incur to ensure health and safety measures at the project sites. As a result, he said, the cost to operate any site has increased.
Why Workers May Be Wary
While workers may be in dire need to jobs as the Indian's economic growth has collapsed because of the lockdown, they are wary of promises. Just a few months ago, they were forced to walk hundreds of kilometres in the absence of any transport. And what was promised at the beginning of the lockdown wasn't delivered.
In April, Maharashtra announced assistance of Rs 2,000 each to active construction worker registered with the Maharashtra Building and Other Construction Worker's Welfare Board.
But, according to a report published by Youth for Unity and Voluntary Action, among the workers living on work sites registered with board, less than a third who received the cash transfer even though 87.64% of them have bank accounts.
Developers Optimistic
The government has started special trains and developers themselves are offering help to bring back workers. After the industry's demand, it announced another 80 long-distance trains from Sept. 12.
That helped another 10% workers to return to Mumbai, a Credai-MCHI spokesperson told BloombergQuint over the phone.
Still, the return of 65% is awaited.
“Many construction workers are cyclical migrants and return to their villages before the monsoon to help sow the Rabi crop,” said Rajan Bandelkar, president, Naredco West, and convener, housingforall.com. “We estimate that the remaining construction workers will return by Dussehra or Diwali.”
-
Ten Things I Learnt This Samvat
Patience can be a trap. Cheap stocks can stay cheap. Leverage can wipe you out. What did Samvat 2082 teach us? Niraj Shah writes on 10 lessons from the year gone by.
-
Talking Points This Week: Tech Nerves, FII Buying, And A Faraway Banking Shock
The global markets are not shining this Diwali. The exception in the large markets is, India.
-
Midterm Rally Lasted A Day. The Hard Reality Of A Divided US May Last Two Years | Opinion
Between a contested AI boom, a debt ceiling that arrives in 2027 and a president with every incentive to act alone, the next two years may prove more volatile than the first day's rally suggests.
-
Blue Wave Will Derail the AI Trade but Won't Dismantle the AI Era | Unhedged Position
The Democrats' sweep of the US Congress will see politics collide with economic forces both over the long and short term.
-
It's Time To Take The GST Council's Bet On Trust Global
Payment records can prove India's services exports, and clear, proportionate rules can bring foreign digital sellers into the tax net.
-
Opinion | India at 38: From Innovation Overperformer to Innovation Powerhouse
India now has 453 VC-backed deep science startups, 18 of them late-stage, after 117 percent growth since 2020. Laurus Labs, at USD 9.3 billion, is the most valuable deep science company in any middle-income economy outside China.
-
Navigating Energy Crossroads: S Jaishankar's Call For Diversified Supply Chains At G20 Ministerial Meeting
As geopolitical fault lines continue to test maritime trade routes and commodity flows, Jaishankar's message remains pertinent: true economic resilience requires open markets, protected transit lines, and a genuine commitment to multilateral cooperation rather than coercion.
-
Indians Are Travelling, But Not Every Journey Is A Holiday | The Week In Whys
Pilgrims, patients and working women are the real travellers, and the system hasn't quite caught up with them.
-
Getting To Work Costs Women More | The Reason Why
It is not just about women paying more than men. It is about women paying much more in cities than in villages.