MMRDA Terminates Monorail Contract With L&T JV
Town planning authority Mumbai Metropolitan Region Development Authority terminated the contract on Friday with the L&T-Scomi Engineering consortium that has been operating the country's first monorail network after the Malaysian company failed to meet contractual obligations despite getting several extensions.
The Mumbai Metropolitan Region Development Authority also took over the project and decided to operate and maintain it, besides deciding to en-cash the Rs 200-crore bank guarantee from the operator.
"Finally, we have terminated the contract with the L&T consortium after granting them seven extensions and to operate and maintain the network on our own in the larger public interest," MMRDA commissioner RA Rajeev told reporters.
The consortium could not be immediately reached for comments.
Blaming Scomi primarily for the termination of the contract, Rajeev said, "L&T was the civil works contractor and had met its contractual obligations by completing the work and so cannot be blamed for our decision. But Scomi failed to meet their contractual obligations of operating and maintaining the project apart from supplying the rolling stock." The L&T-Scomi consortium won the Rs 2,460-crore contract in 2009 to build and operate the 19.5-km monorail network on the Chembur-Wadala-Jacob Circle corridor connecting the eastern periphery of the island city to the central parts.
The authority had slapped a show-cause notice to the operator on Dec. 7 and the consortium has given an interim reply on Dec. 13, he said.
Under the consortium agreement, L&T was responsible for the entire civil work, electrical and automation, Scomi Engineering, which one of the world's top three monorail manufacturers, had to bring in the rolling stocks, signaling and other operation and maintenance side of the project.
L&T was to execute the Engineering, Procurement and Construction side of the contract, Scomi was to supply the rolling stocks, singalling and other operations side of the project.
Rajeev said the consortium was given a long rope to enable them to recover from cash crunch, but they failed to supply the rolling stocks and also operate and maintain the 8.9-km corridor.
“As per the contract, the consortium had to supply 15 rakes, however, Scomi had supplied only 10. Of these 10 rakes, only four are operational,” Rajeev said.
"We cannot continue to grant more extensions. We have decided to terminate the entire contract after they have failed to respond to our legal notices. Now, we are in the process of issuing fresh tenders to procure additional rakes," Rajeev said.
The first phase of the line, stretching 8.9 km between Chembur and Wadala, was commissioned in February 2014, against the original deadline of 2010.
Rajeev further said the Rs 200-crore received as bank guarantee from the consortium will be en-cashed.
"The authority has already paid Rs 67 crore to the consortium in 2015 to overcome their cash crunch and another Rs 16.34 crore was paid between February and October 2017.
However, they failed to even pay the rent for the casting yard, despite several reminders.
"Since Scomi has failed to meet its obligations, we have decided that the bank guarantee paid by the consortium will be treated as penalty," he said.
He further said following the termination of the contract, 198 Indians working on the project, will be absorbed by the authority.
The authority had first proposed the monorail in November 2005 and in 2008, the contract for the 18.5 km long first-line connecting Jacob Circle, Wadala and Mahul via Chembur was awarded to L&T, along with the Malaysian firm.
The state had also planned to construct nine other monorail corridors, however, with the failure of the pilot project, it abandoned the plan to build a 190-km of monorail network across the Mumbai metropolitan region.
The entire 19.5-km Chembur-Wadala-Jacob Circle corridor was due to start in December 2010, but instead, only an 8.9-km line between Chembur and Wadala under phase 1 was finally opened on Feb. 2, 2014.
However, the operations were shut after a coach went up in flames on Nov. 9, 2017, while the phase 2 between Wadala and Jacob Circle is yet to be commissioned.
The commissioner further said the second phase will be commissioned in the next three months.
"We will be issuing global tenders not only for spare parts and tyres for replacement, but also for additional 10 rakes. We hope in the next three months we will be able to commission the second phase depending on when we get the rakes," he said.
-
High US Salaries, No Green Card Certainty: The Financial Calculation Facing Indian H-1B Families
The suspension of PERM processing at eight technology employers does not cancel existing H-1B visas. What it does is force a question many Indian families have been avoiding: is the US salary worth tying your career and family plans to one employer?
-
Unhedged Position: Can India See An Indonesia-Style Time Correction?
The Nifty is trading below levels it first clocked in 2024. Is there, then, as I have suggested in the headline, potential that the current time correction drags on painfully for the next three-five, even ten years?
-
Navigating Friction And Energy Realities: An Analysis Of Marco Rubio's October Visit To India
Occurring at a critical juncture marked by stalled trade negotiations and escalating geopolitical pressures over global energy supplies, the visit offers a profound window into modern US-India relations.
-
India Exports Capital. Why Not Export Trusteeship?
The big question, then, is whether India can build an institution that global borrowers, investors, banks, and lawyers can trust, even without an Indian connection.
-
France's Economy & Politics Are In Crisis | The Reason Why
Let's look at how the French economy and politics evolved under Nicolas Sarkozy, Franois Hollande and Emmanuel Macron.
-
You May Inherit The Business. You Must Earn Its Credibility.
Succession tests the founder's ability to share authority as much as it tests the next generation's readiness to assume it.
-
Signing Deals Is One Thing; Making Them Work Is Another | The Week In Whys
Sometimes, things don't turn out as planned. Indian companies have lost some bids to rivals, some projects won't produce until 2030.
-
FOMC Wall, PERM Suspension, Hospital Stocks | Talking Points This Week
A PERM suspension would directly affect green-card sponsorship rather than H-1B visas, so the near-term earnings impact could remain relatively limited. The key question is whether this marks a new phase in US scrutiny of Indian IT.
-
Everything, Everywhere, All At Once: Dalal Street's Week To Forget | Joining The Dots
Visa curbs, a Starlink spat and cancer drug caps: what connects this week's shocks for Indian markets
-
India Is Going Abroad For Critical Minerals. But It May Take Years To Pay Off | The Reason Why
Although India's steps are in the right direction, they remain modest compared with India's growing dependence.