Top Copper Producer Delays Full Restart of Chile Smelter
(Bloomberg) -- Top copper producer Codelco is again delaying the return to normal operations at its Chuquicamata smelter.
Some parts of the smelter are operating normally, including the flash oven and one acid plant, a Codelco official said in an email in reply to questions from Bloomberg. A second acid plant will start ramping up within the next six days and the whole facility is expected to be up and running within the third quarter, the company said.
In April, Codelco Chairman Juan Benavides said the plant would be fully operational by mid-year at the latest. The facility has remained shut for more than seven months, as Codelco failed to complete the works necessary to comply with tougher environmental standards that were implemented in December.
The facility is unlikely to return to normal capacity until mid-August, Rolando Milla, president of Chuquicamata Union No. 3 and union coordinator at the smelter, said in an interview Wednesday. The cancellation of Codelco's contract with engineering firm SNC Lavalin Group Inc. forced the company to push back the timeline for the restart, he said.
‘All Sorts of Delays'
The smelter's flash oven is now processing 70 to 80 tons of concentrate per hour, well below its normal capacity of 180 tons per hour, Milla said. Other parts of the plant aren't fully operational, he said in an interview in nearby Calama.
“The use of contractor companies instead of Codelco's own workers has resulted in all sorts of delays over the last few months,” Milla said. “We are asking our workers to get the smelter and the rest of the operations up and running as soon as possible – the company can't blame us for these delays.”
A majority of Chuquicamata workers downed tools for two weeks last month amid a labor contract dispute with the company. Before the strike, Codelco had canceled its contract with SNC-Lavalin amid delays in the construction of two new acid plants at the smelter. Codelco took over the work after the contract was rescinded. Copper in London was little changed at $5,919 a ton on Thursday.
‘More Stringent'
The delay will likely result in another month of higher-than-normal concentrate shipments from Codelco, Colin Hamilton, a BMO Capital Markets analyst, said in a research note on Thursday. “Given that environmental legislation in Chile is only becoming more stringent, we would not be surprised to see smelting facilities in the country close over time.”
The Chuquicamata mine was working at very limited capacity during last month's strike, said Milla and Union No. 2 president Liliana Ugarte, contradicting an earlier company statement that it had been running at over 50% capacity.
During the strike, 14 trucks were operating at the mine's pit -- the world's largest in size -- compared with 70 to 80 trucks during normal times, Milla said. Workers are struggling to ramp up output to normal level as the two-week stoppage resulted in a backlog in some parts of the operation, Ugarte said in a separate interview in Calama on Wednesday.
To contact the reporter on this story: Laura Millan Lombrana in Santiago at lmillan4@bloomberg.net
To contact the editors responsible for this story: Luzi Ann Javier at ljavier@bloomberg.net, Steven Frank
©2019 Bloomberg L.P.
-
Indians Stay With Family, Not In Hotels | The Reason Why
India still lacks enough clean, reliable and affordable hotels for budget-conscious travellers.
-
The Economic Imperative: Analysing The Material Driving Force Behind India-Canada Strategic Reset
This economic complementarity is further reinforced by deep institutional investment ties and talent mobility, which form the bedrock of the bilateral framework.
-
Medicine Pricing: Where Must Profit Stop?
India must confront excessive margins, hidden incentives and regulatory gaps that threaten the integrity of medicine.
-
Why Amazon And Flipkart Are Struggling To Beat Meesho In India's Smaller Cities
With 274 million users and lowest-cost logistics, Meesho is defending its value commerce crown against giants like Amazon and Flipkart.
-
High US Salaries, No Green Card Certainty: The Financial Calculation Facing Indian H-1B Families
The suspension of PERM processing at eight technology employers does not cancel existing H-1B visas. What it does is force a question many Indian families have been avoiding: is the US salary worth tying your career and family plans to one employer?
-
Swiggy vs Eternal: Food Delivery's Two Rivals Are No Longer In The Same Race
Eternal is building a private AI assistant, dark.ai. Swiggy is still working out how to make Instamart pay, with an operating loss of Rs 895 crore in the July-September quarter while Blinkit stayed profitable.
-
Where You Live Shapes How You Get To Work | The Reason Why
Two-wheelers are the most popular way to get to work in India, accounting for nearly 43% of workplace commutes.
-
Unhedged Position: Can India See An Indonesia-Style Time Correction?
The Nifty is trading below levels it first clocked in 2024. Is there, then, as I have suggested in the headline, potential that the current time correction drags on painfully for the next three-five, even ten years?
-
Navigating Friction And Energy Realities: An Analysis Of Marco Rubio's October Visit To India
Occurring at a critical juncture marked by stalled trade negotiations and escalating geopolitical pressures over global energy supplies, the visit offers a profound window into modern US-India relations.
-
India Exports Capital. Why Not Export Trusteeship?
The big question, then, is whether India can build an institution that global borrowers, investors, banks, and lawyers can trust, even without an Indian connection.