Raytheon's GPS III Ground Control Network Slips Once Again
(Bloomberg) -- Add at least nine more months of delays before the U.S. Air Force can deploy a fully capable version of Raytheon Co.'s ground system for advanced GPS satellites, a project that was already running about five years late.
The ground system, which was supposed to be in operation by October 2016 under Raytheon's contract, now isn't projected to be ready until at least April 2022, the Air Force said in response to an inquiry by Bloomberg News. Extending the schedule will increase the projected cost of the system's development phase to $6 billion, up from $5.4 billion most recently and $4 billion in 2015.
Raytheon's “Operational Control Network” of 20 ground stations and antennas worldwide is needed to take full advantage of new GPS III satellites being built by Lockheed Martin Corp. that promise greater worldwide coverage, accuracy and cybersecurity. The Global Positioning System is widely used for everything from helping the military to pinpoint airstrikes against Islamic State to allowing civilians to map street-by-street driving directions on their smartphones.
The new satellites also have been beset by repeated delays, with the first launch now planned the second quarter of 2018.
“The Air Force has implemented improvements across the program, including at Raytheon,” Captain AnnMarie Annicelli, an Air Force spokeswoman, said in an email. “These include development of contingency efforts and modernizing software development processes. GPS is important to every American, and the Air Force must get it right.”
It's been “a troubled program from the beginning,” Annicelli said. “We are placing a lot of pressure on the contractor, and expect Raytheon to do the job they are contracted to perform.”
Absorbing Overrun
The Air Force proposed the delay in the ground stations to Pentagon officials in June during a major review of the troubled program. The service said it will need to find an additional $630 million after 2019 because of the latest delay, but has funds through fiscal 2018. The service must absorb the overrun under the “cost-plus” award fee contract it signed with Raytheon in February 2010.
After a 24-month delay set last year, “further analysis” resulted “in a more realistic schedule baseline extension of 33 months,” Annicelli said. “The increased schedule was due in part to realized program technical risks, and includes hardware and software obsolescence,” she said.
The network from Waltham, Massachusetts-based Raytheon was called the Pentagon's “No. 1 troubled program” last year by the Air Force's head of space systems acquisition.
“We remain on track to deliver this essential, advanced capability” based on an Air Force decision in March, before the Pentagon review, “to add an additional six months of margin,” Mike Doble, a Raytheon spokesman, said in a statement. He said he couldn't address the Air Force's latest “pre-decisional” extension.
Raytheon's current schedule, even with doubling its staff to more than 1,000 personnel, assumes “efficiencies from software engineering improvements, such as increased testing automation, that have not yet been demonstrated,” the Government Accountability Office said in a May report.
To contact the reporter on this story: Tony Capaccio in Washington at acapaccio@bloomberg.net.
To contact the editors responsible for this story: Bill Faries at wfaries@bloomberg.net, Larry Liebert, Ros Krasny
-
The Economic Imperative: Analysing The Material Driving Force Behind India-Canada Strategic Reset
This economic complementarity is further reinforced by deep institutional investment ties and talent mobility, which form the bedrock of the bilateral framework.
-
Medicine Pricing: Where Must Profit Stop?
India must confront excessive margins, hidden incentives and regulatory gaps that threaten the integrity of medicine.
-
Why Amazon And Flipkart Are Struggling To Beat Meesho In India's Smaller Cities
With 274 million users and lowest-cost logistics, Meesho is defending its value commerce crown against giants like Amazon and Flipkart.
-
High US Salaries, No Green Card Certainty: The Financial Calculation Facing Indian H-1B Families
The suspension of PERM processing at eight technology employers does not cancel existing H-1B visas. What it does is force a question many Indian families have been avoiding: is the US salary worth tying your career and family plans to one employer?
-
Swiggy vs Eternal: Food Delivery's Two Rivals Are No Longer In The Same Race
Eternal is building a private AI assistant, dark.ai. Swiggy is still working out how to make Instamart pay, with an operating loss of Rs 895 crore in the July-September quarter while Blinkit stayed profitable.
-
Where You Live Shapes How You Get To Work | The Reason Why
Two-wheelers are the most popular way to get to work in India, accounting for nearly 43% of workplace commutes.
-
Unhedged Position: Can India See An Indonesia-Style Time Correction?
The Nifty is trading below levels it first clocked in 2024. Is there, then, as I have suggested in the headline, potential that the current time correction drags on painfully for the next three-five, even ten years?
-
Navigating Friction And Energy Realities: An Analysis Of Marco Rubio's October Visit To India
Occurring at a critical juncture marked by stalled trade negotiations and escalating geopolitical pressures over global energy supplies, the visit offers a profound window into modern US-India relations.
-
India Exports Capital. Why Not Export Trusteeship?
The big question, then, is whether India can build an institution that global borrowers, investors, banks, and lawyers can trust, even without an Indian connection.
-
France's Economy & Politics Are In Crisis | The Reason Why
Let's look at how the French economy and politics evolved under Nicolas Sarkozy, Franois Hollande and Emmanuel Macron.