Zimbabwe, Zambia Hydropower Plant Upgrade Delayed by Two Years

Zimbabwe, Zambia Hydropower Plant Upgrade Delayed by Two Years

Upgrades to Kariba Dam, the main source of electricity for Zambia and Zimbabwe, have been set back by at least two years because of technical challenges and supply disruptions caused by the coronavirus pandemic, the Zambezi River Authority said.

A meeting of finance ministers from the two countries last week cited delays in contracting works, unforeseen technical challenges and supply constraints for the delay, the authority, which regulates water usage, said.

The ministers approved a budget of $71.3 million for 2021 that will be financed through a combination of internally generated funds, amortized loans and grants sourced from the World Bank, African Development Bank, the European Union and the Swedish International Development Agency.

Kariba, which has the capacity to produce 1,050 megawatts of electricity, has been operating below capacity because technical faults and low water levels in the dam caused by past successive droughts.

READ: Zimbabwe's Kariba Plant Nears Capacity for First Time Since 2018

©2021 Bloomberg L.P.

Essential Business Intelligence, Sharp Market Insights, Practical Personal Finance Advice, Daily Fuel, Gold and Silver Prices and Latest Stories — On NDTV Profit.

Newsletters

Update Email
to get newsletters straight to your inbox
⚠️ Add your Email ID to receive Newsletters
Note: You will be signed up automatically after adding email

News for You

Set as Trusted Source
on Google Search
Add NDTV Profit As Google Preferred Source
Listen to the latest songs, only on JioSaavn.com