Nuclear Power: SCE&G, Santee Cooper Plant Victim Of New Reality
(Bloomberg Gadfly) -- A good explanation of why two half-finished nuclear reactors in South Carolina are being canned came in a press release sent out Monday afternoon by the Nuclear Energy Institute lamenting the decision:
We applaud SCE&G [South Carolina Electric & Gas] and Santee Cooper's valiant and visionary efforts to embark upon a new nuclear construction project for the first time in this country in more than 30 years. As a first-of-a-kind nuclear construction project of this size and scope, the project understandably encountered many economic, regulatory and other challenges along the way.
I think we can all agree that building a nuclear power plant is quite an undertaking. And that's doubly so when it's been a generation or more since anyone else started building one in the U.S. and you're attempting a "first-of-its-kind" project, to boot.
Westinghouse Electric Co. was first contracted to build the reactors by Scana Corp.'s SCE&G and state-owned power company Santee Cooper back in 2008, and the first concrete was poured at the site 4 years ago. This year, mired in cost overruns associated with this project and another for Southern Co. in Georgia, Westinghouse declared bankruptcy. The plant was originally supposed to cost about $11 billion, or just over $4,900 per kilowatt of capacity. In a report published in March, as Westinghouse was wobbling, Morgan Stanley estimated the cost had more than doubled to more than $10,000 per kW. By way of comparison, a modern plant running on natural gas costs about $1,100 per kW.
Today, any U.S. energy project scheduled to take a decade to get up and running and which costs billions of dollars faces a fundamental problem: The country's energy market is being turned on its head.
When the reactors were first ordered, demand for electricity in the South Atlantic region -- which includes South Carolina -- was projected by the Department of Energy to rise by almost 40 percent by 2030. Those numbers have since collapsed utterly:
Meanwhile, the price of natural gas has slumped as a result of the shale boom, which wasn't widely understood back in 2008. Gas has since gone from being regarded as a volatile market to being accepted as a low-cost source of fuel supply for generators, helping to depress wholesale electricity prices in general:
Throw in the fact that the cost of renewable energy sources has also fallen dramatically -- and has tended to depress electricity prices
What compounds this for nuclear power is that the specific needs, regulatory and otherwise, of each project make it hard to achieve scale economies. If each plant requires a different approach, how do you gain efficiency, especially after several decades of inactivity have eroded America's capabilities in the field? Repeatable technologies, with falling costs, tend to do best.
This isn't necessarily the case in other countries such as China, where it may be possible to deploy the same type of plant in multiple locations with the backing of national planning.
But the U.S. is different. This study of construction costs for nuclear plants published in early 2016 found that unit costs for plants under construction at the time of the Three Mile Island accident surged compared to those completed before 1979, most likely because of increased safety requirements and delays. The fact that Westinghouse couldn't keep a lid on costs and delays despite being contracted to build four of the same reactor type in the U.S. merely confirms this challenge.
Given the inherent uncertainties around U.S. electricity demand and the balance between liberalized and regulated power markets, it is nigh on impossible to justify plowing billions into a big, complex nuclear-power plant supposed to run for 50 or 60 years. Widespread carbon pricing or piecemeal support efforts for existing nuclear plants, such as those enacted in Illinois or New York, offer some support.
But to have any chance, new nuclear power would need to be smaller, more modular and faster-to-market -- like the natural gas and renewable-power sources with which it competes in a flat market.
This column does not necessarily reflect the opinion of Bloomberg LP and its owners.
Liam Denning is a Bloomberg Gadfly columnist covering energy, mining and commodities. He previously was the editor of the Wall Street Journal's "Heard on the Street" column. Before that, he wrote for the Financial Times' Lex column. He has also worked as an investment banker and consultant.
To contact the editor responsible for this story: Mark Gongloff at mgongloff1@bloomberg.net.
-
Indians Stay With Family, Not In Hotels | The Reason Why
India still lacks enough clean, reliable and affordable hotels for budget-conscious travellers.
-
The Economic Imperative: Analysing The Material Driving Force Behind India-Canada Strategic Reset
This economic complementarity is further reinforced by deep institutional investment ties and talent mobility, which form the bedrock of the bilateral framework.
-
Medicine Pricing: Where Must Profit Stop?
India must confront excessive margins, hidden incentives and regulatory gaps that threaten the integrity of medicine.
-
Why Amazon And Flipkart Are Struggling To Beat Meesho In India's Smaller Cities
With 274 million users and lowest-cost logistics, Meesho is defending its value commerce crown against giants like Amazon and Flipkart.
-
High US Salaries, No Green Card Certainty: The Financial Calculation Facing Indian H-1B Families
The suspension of PERM processing at eight technology employers does not cancel existing H-1B visas. What it does is force a question many Indian families have been avoiding: is the US salary worth tying your career and family plans to one employer?
-
Swiggy vs Eternal: Food Delivery's Two Rivals Are No Longer In The Same Race
Eternal is building a private AI assistant, dark.ai. Swiggy is still working out how to make Instamart pay, with an operating loss of Rs 895 crore in the July-September quarter while Blinkit stayed profitable.
-
Where You Live Shapes How You Get To Work | The Reason Why
Two-wheelers are the most popular way to get to work in India, accounting for nearly 43% of workplace commutes.
-
Unhedged Position: Can India See An Indonesia-Style Time Correction?
The Nifty is trading below levels it first clocked in 2024. Is there, then, as I have suggested in the headline, potential that the current time correction drags on painfully for the next three-five, even ten years?
-
Navigating Friction And Energy Realities: An Analysis Of Marco Rubio's October Visit To India
Occurring at a critical juncture marked by stalled trade negotiations and escalating geopolitical pressures over global energy supplies, the visit offers a profound window into modern US-India relations.
-
India Exports Capital. Why Not Export Trusteeship?
The big question, then, is whether India can build an institution that global borrowers, investors, banks, and lawyers can trust, even without an Indian connection.