(Bloomberg) -- The Federal Emergency Management Agency spent $35.1 million on renting two emergency generators to help power blacked-out San Juan, Puerto Rico. But a group of engineers says existing infrastructure could have been used more effectively at a fraction of the cost.
The mobile turbine generators, fully connected as of last week, bring some 50 megawatts to the partially idled Palo Seco plant west of the capital. That's intended to stabilize power supply, at least in neighborhoods where distribution lines are intact.
Yet the Puerto Rico Professional College of Engineers and Land Surveyors said a better alternative was to turn on some of Palo Seco's existing facilities to provide at least five times more power, according to a report delivered to local lawmakers and an interview with the organization's president. Members of the group toured the plant Oct. 19 with a Senate delegation led by Larry Seilhamer, vice president of the body and an engineer by training.
About 70 percent of Puerto Ricans are still without electricity, including vast swaths of the capital of around 350,000 people. Pablo Vazquez Ruiz, president of the engineering college, said last week that the new generators will probably be insufficient for Puerto Rico's most populous and economically important region.
“We're in an emergency,” Vazquez Ruiz said. “We're spending a lot of money with this, and we're not supplying enough power to the metropolitan area."
The generators were rented through a contract with Weston Solutions, a West Chester, Pennsylvania-based disaster response company. FEMA provided funding to the U.S. Army Corps of Engineers for such projects, and the Army Corps in turn assigned the contract to Weston.
Power Flashpoint
The provision of power six weeks after Hurricane Maria has become a flashpoint in a difficult and politically sensitive recovery.
The engineers' findings come as federal lawmakers scrutinize a $300 million contract that Puerto Rico gave to Whitefish Energy Holdings LLC when it was a two-employee Montana-based company. In addition to the company's tiny size, it has attracted attention because its previous known contracts were a fraction the size of the Puerto Rico deal, and it is based in the small hometown of Interior Secretary Ryan Zinke. Zinke and Whitefish have denied he played any role in the deal.
The uproar prompted the commonwealth to request the contract's cancellation.
The concerns about Palo Seco reflect broader questions about FEMA money. In June, Inspector General John Roth warned of the agency's “continued failure to manage disaster relief funds adequately," in a letter to the chairman of the Senate Committee on Homeland Security and Governmental Affairs.
Like much of the infrastructure of the bankrupt Puerto Rico Electric Power Authority, or Prepa, the Palo Seco plant is in decay. In August, the utility announced it would shut down its four boiler-and-turbine units as long as six months for repairs and rely on power from other plants for San Juan.
Prepa hired General Electric Co. to repair the structure that supports the boilers. In an emailed statement, Katie Jackson, a GE spokeswoman, said the company “isn't under contract to repair the boilers or the steam turbine units at Palo Seco. GE is only under contract to repair the structure that supports the boilers.”
She didn't address the question of whether the job could be accelerated, but said the company anticipates “exploring other opportunities to help.”
Corrosion in structural framing posed “a current imminent threat to the safety of personnel," according to a report by West Islip, New York-based Island Structures Engineering PC, a sub-consultant. Pictures in the report showed rust and other degradation to the structures, which were built in the 1950s and 1960s and sit just yards from the Bay of San Juan.
Mothballed Equipment
But Puerto Rican engineers now say the crisis should prompt the government to revisit its decision. If nothing else, the government should demand that GE -- which is charging about $5 million -- provide an accelerated timetable that focuses on the most essential tasks, Vazquez Ruiz said.
He said one boiler could be running safely in less than two weeks, and two could be going in three weeks. Another apparently usable boiler was disabled to connect the rental generators, Vazquez Ruiz said.
“Why would you spend that taxpayer money when you could fix this" with the money already paid to GE, said Vazquez Ruiz, a former Army Corps deputy district engineer whose responsibility included oversight of Puerto Rico.
Ramon Rosario, Puerto Rico's public affairs secretary, told reporters last week that the government would consider the engineers' findings. But in an emailed statement Tuesday, Rosario said the government considered the Island study “conclusive,” based on a more thorough inspection by a company that had been monitoring the plant for years.
By comparison, he said, the College of Engineers report was based on a visual assessment over a few hours. He also said the engineers didn't evaluate the plant when the machinery was turned on, referencing a disclosure in the report itself. “They did not do other necessary tests," he said.
Jeffrey Hawk, a spokesman for the Corps of Engineers in Puerto Rico, said the generators were rented to execute a mission assigned by FEMA, which is funding much of Puerto Rico's recovery efforts. FEMA referred questions on the matter to the Corps of Engineers. Prepa didn't respond to a request for comment.
San Juan Mayor Carmen Yulin Cruz said the engineers' study should be taken seriously.
“I respect the College of Engineers," she said. “They have no political agenda. They are licensed engineers, so they wouldn't be saying something should work if something does not work, because their reputations are at stake."
Meanwhile, the idled plant has angered residents eager to return to normalcy. On a recent day, graffiti on a cement wall outside the plant read: “Turn it back on!"
--With assistance from Michael Smith Richard Clough and Christopher Flavelle
To contact the reporters on this story: Jonathan Levin in San Juan, Puerto Rico, at jlevin20@bloomberg.net, Naureen S. Malik in New York at nmalik28@bloomberg.net.
To contact the editors responsible for this story: Michael J. Moore at mmoore55@bloomberg.net, Flynn McRoberts, Stephen Merelman
©2017 Bloomberg L.P.
-
One Battle After Another: India's Corporate Dynasties Battle For Control
2026 could go down as Corporate India's year of succession wars, governance battles and family fault lines.
-
Rs 50-Lakh Gold In Bank Locker, Rs 3 Lakh Of Protection: The Gap Most Families Don't Know About
The RBI ties a bank's liability to the annual locker rent and families who want to insure their jewellery face a separate question about how to prove what was inside.
-
The More Food Turns Into Fuel, The Harder It Is To Read Agricultural Markets | The Reason Why
A policy designed to reduce dependence on imported fuel can create new pressures elsewhere in the food economy.
-
Your iPhone Costs 12 Grams Of Gold, A Car About 100. What Does Your Life Weigh?
Measured in rupees, almost everything looks more expensive than it did a generation ago. Measured in grams of gold, a lot of it has become cheaper.
-
Gold Is Rs 22,000 Cheaper Than A Month Ago. Should You Buy Amid The Wedding Season?
Gold's potential slide to $3,500 could save around Rs 4,700 per 10 grams, but a soft inflation print could just as easily push prices back up. One way to split the risk is to buy in parts, some now and the rest after the Fed's Dec. 9 decision.
-
AI Agents Are Gaining Power. Who Governs Them?
Artificial intelligence agents promise to transform productivity by moving machines from assisting decisions to executing them. But as organisations delegate greater authority to these AI-agents, they must first establish who controls that authority and who remains accountable when things go wrong.
-
Why Swapping Your Old Gold Can Trigger A Rs 5 Lakh Tax Bill, And How You Can Avoid It Legally
Swapping old gold for new is taxed as a sale and a fresh purchase. Getting your own gold remade can cut most of that bill, though it has its own costs.
-
The AI Trade is Done. The Real Opportunity for Investors Starts in 2027 | Unhedged Position
As pureplay AI stocks plunge and circular, capex-led financing unwinds, 2027 is set to be a year of reckoning for AI companies. Yet the bust clears the way for a better opportunity for investors in 2027 -- shifting the spotlight from AI builders to the companies using AI.
-
Leadership As Mission: Why The Age Of AI Demands More Human Leadership
Debjani Ghosh examines how AI is changing leadership, arguing that its success must be measured by its impact on people and the accountability of those guiding its use.
-
We May Need Another Tukaram Mundhe To Fight Air Pollution | The Reason Why
Developers may install basic measures such as sprinklers and green nets, resume work, and continue violating rules when this equipment stops working.