Delhi Metro To Build India's Longest Corridor, Completes Civil Work On Pink Line's 'Missing' Link
Delhi Metro authorities completed the civil work on the Pink Line's 'missing' section - between Mayur Vihar Pocket 1- Trilokpuri Sanjay Lake, by installing steel girders, instead of concrete girders, for joining the two ends of the Pink Line corridor, resulting in a single metro stretch between the 58.6-km Majlis Park to Shiv Vihar. This metro corridor - which will be extended from Majlis Park to Maujpur under the Delhi Metro Phase – IV project, covering a distance of approximately 70 km, will become the longest single metro corridor in the country.Â
Metro authority Delhi Metro Rail Corporation (DMRC) installed a total of 40 steel girders over 10 spans for the 290 m long Mayur Vihar Pocket 1- Trilokpuri Sanjay Lake section, which was earlier missing. This led to metro trains operating on two separate sections of the Pink Line, presently being Majlis Park- Mayur Vihar I and Shiv Vihar-Trilokpuri sections.
Â
Delhi Metro Pink Line 'Missing' Link: Why was construction delayed?
A senior metro official told NDTV that the construction work on the missing link between Mayur Vihar Pocket 1- Trilokpuri Sanjay Lake got delayed due to land acquisition and rehabilitation issues. ​An encumbrance-free land was unavailable in this area, and metro authorities acquired the required land following the due process of law. The houses and residents affected due to the metro line were rehabilitated, after which DRMC began the construction work.Â
The construction or civil work started on this metro stretch in early 2020, however, the pace was repeatedly hindered due to the COVID-19 induced lockdowns. The steel girders varying between 16 to 38 metres in length were installed and the casting of the deck slab was completed in April 2021, just before the second wave of the pandemic. Â
Metro authorities used steel girders instead of the conventional concrete girders as the construction of the concrete ones would have required the establishment of a casting yard. Setting up a casting yard would not have been feasible for a small stretch in a short period of time. Due to this reason, steel girders were installed on the section.
Delhi Metro Pink Line: By when will it operate as a single corridor?
The civil work between the Mayur Vihar Pocket – 1 and Trilokpuri Sanjay Lake stretch is completed and track laying and other ancillary works have started. The overhead electrification (OHE) work on the stretch is also under progress.Â
The track laying work is expected to be completed by the end of this month and preliminary trials are then expected to start. The section will be operational for services immediately after receiving the mandatory clearances from concerned authorities. A DMRC official told NDTV that the entire process is likely to take around two-three months.
Delhi Metro Pink Line: How will it benefit commuters?
Once the construction between Mayur Vihar Pocket 1- Trilokpuri Sanjay Lake is completed, it will connect the two ends of the Pink Line and will provide straight connectivity to far-flung localities in the national capital region (NCR).
The important transport hubs such as Anand Vihar ISBT, Nizamuddin railway station, Anand Vihar railway station, Sarai Kale Khan ISBT, Delhi Cantt. station and markets such as Lajpat Nagar, Sarojini Nagar, and Dilli Haat - INA will get direct metro connectivity through the Pink Line.
Moreover, after the completion of the Delhi Metro Phase IV - which will make the Pink Line the longest operational metro corridor in India, it will also become the only ring corridor of metro in the country, according to DMRC.
-
We May Need Another Tukaram Mundhe To Fight Air Pollution | The Reason Why
Developers may install basic measures such as sprinklers and green nets, resume work, and continue violating rules when this equipment stops working.
-
Extracting Value From Battery Scrap Could Be Challenging For India | The Reason Why
A discarded lithium-ion battery still contains valuable materials such as lithium, nickel and cobalt. These can be recovered and reused. When such batteries are crushed and shredded, they produce a dark powder called black mass.
-
One El Nino, India Can Handle. Two Could Break The Granary
India's grain stocks can absorb one bad year, but a second El Nino could drain the buffer in two to three years, economists say.
-
India's Troika Of Good Luck | Joining The Dots
As Jensen Huang's exit drags Nvidia down, a cooling AI trade and resilient earnings have revived investor interest in India. A likely RBI rate hike looms.
-
Talking Points This Week: Leadership Shock At Nvidia, Earnings Strength, And The Fog Over Hormuz
The Anthropic IPO pricing and first trading day, Nvidia's upcoming earnings, and any fresh signals from Iran will set the tone for the following week.
-
Signature Play: The Classic Cocktail Is Dead. Or Is It?
Classic cocktails are disappearing from India's cocktail menus. But they're still being ordered, taught to bartenders and borrowed from. So, who's really having the last drink?
-
A New Samvat Wishlist: Inclusive Prosperity And Human Development
India has strengthened its economic foundations through infrastructure, digital access and enterprise. Its next growth chapter must deepen productivity, create better livelihoods and widen participation in prosperity.
-
Love, Sex Aur Dhokha: The Audacious Plot To Spy On Jensen Huang
A Taipei dinner, a Singapore chip buyer and a suspected Chinese asset: inside the alleged spy operation that got close to NVIDIA's Jensen Huang.
-
Ten Things I Learnt This Samvat
Patience can be a trap. Cheap stocks can stay cheap. Leverage can wipe you out. What did Samvat 2082 teach us? Niraj Shah writes on 10 lessons from the year gone by.
-
Talking Points This Week: Tech Nerves, FII Buying, And A Faraway Banking Shock
The global markets are not shining this Diwali. The exception in the large markets is, India.