Coal India August Output at 34.5 MT; Target Missed

New Delhi: Coal India produced 34.54 million tonnes of coal in August, missing its target for the fourth consecutive month, even as acute fuel shortages continue to hit power generation.

The target for the month was 35.13 million tonnes (MT).

In the first five months of the current fiscal year (2014-15), Coal India produced 175.88 MT of coal against the target of 183.44 MT, the company said in a filing to the BSE.

In May, the output was 36.27 MT against the target of 38.46  MT.

The production was 34.54 MT in June (against the targeted 36.84 MT) and 33.01 MT in July against a targeted 35.86 MT.

According to the latest data from the Central Electricity Authority (CEA), 56 power plants had less than seven days of coal stocks as on August 31.

Coal and Power Minister Piyush Goyal had earlier asked Coal India to ramp up production from its existing mines.

CIL, which accounts for 80 per cent of domestic coal production, missed its output target of 482 million tonnes for 2013-14, producing 462 million tonnes during the period.

Production fell short of target because of various reasons, including lack of environment clearance to coal mining projects.

In 2012-13, the company produced 452.5 million tonnes of coal, falling short of the 464 MT target.

Coal India's production target for 2014-15 has been set at 507 MT.