CERC Proposes Restricted Grid Access To Boost Efficiency Of Transmission Networks
In a bid to optimise India's inter-state power transmission network, the central electricity regulator has introduced a draft amendment regulation, restricting access to the grid during solar and non-solar hours.
The draft regulation — named Central Electricity Regulatory Commission (Connectivity and General Network Access to the inter-State Transmission System) (Fourth Amendment) Regulations, 2025 — aims to increase the efficiency of the transmission infrastructure, alleviating connectivity issues for renewable energy projects.
The new 'restricted access' policy proposes renewable energy sources to schedule injections into the grid during specific hours, depending on the nature of the energy source. For instance, solar projects will only have access to the grid during solar hours, while wind energy or energy storage systems will utilise the same transmission infrastructure during non-solar hours.
“NLDC shall notify the solar hours and non-solar hours beginning from date of notification of these amendments on a weekly basis for each State. NLDC may revise such hours during the week in case of unforeseen contingency, including weather changes,” the draft regulation noted.
This approach is expected to release a significant amount of blocked transmission capacity, providing relief to the wind energy sector, which has long struggled with connectivity issues. The regulation will enable hybrid projects to optimise their transmission capacity, making the most of the available infrastructure.
For example, a hybrid project with 700 MW of solar, 400 MW of wind, and 200 MW of ESS will have access to 1,000 MW of transmission capacity during solar hours and 600 MW during non-solar hours. This flexibility will enable project developers to maximise their energy output, while minimising transmission losses.
Renewable energy projects based on wind or energy storage systems can now apply for connectivity at inter-state transmission substations with scheduling rights for non-solar hours. Conversely, solar-based projects or renewable hybrid projects will have restricted scheduling during non-solar hours, unless they integrate with other sources like wind or storage.
“The draft regulation aims to release ‘blocked' transmission capacity for faster capacity addition and effective utilisation of transmission infrastructure,” JM Financial Institutional Securities said in a report,
“We believe this, coupled with recent changes in tariff based competitive bidding guidelines for RE projects, is a significant move to relieve the ‘connectivity' pain of the wind energy sector, and these steps are aimed at enhancing the integration of renewable energy, particularly solar and wind power, into the grid by introducing generation-specific restricted access and scheduling rights.”
-
Foreign Investors Own Half Of HDFC Bank and ICICI Bank. An LTCG Cut Could Matter Most Here
Foreign portfolio investors have US$115 billion parked in HDFC Bank, ICICI Bank. If the government cuts long-term capital gains tax, Jefferies says returning foreign money could land here first.
-
'Never Seen This Level Of Negativity': Sandeep Tandon Says The Next Rally May Be Closer Than You Think
Veteran investor Sandeep Tandon says foreign selling is easing, large-caps are due a comeback and mid-caps are crowded, while he turns positive on gold, power and pharma this Diwali.
-
Indians Stay With Family, Not In Hotels | The Reason Why
India still lacks enough clean, reliable and affordable hotels for budget-conscious travellers.
-
The Economic Imperative: Analysing The Material Driving Force Behind India-Canada Strategic Reset
This economic complementarity is further reinforced by deep institutional investment ties and talent mobility, which form the bedrock of the bilateral framework.
-
Medicine Pricing: Where Must Profit Stop?
India must confront excessive margins, hidden incentives and regulatory gaps that threaten the integrity of medicine.
-
Why Amazon And Flipkart Are Struggling To Beat Meesho In India's Smaller Cities
With 274 million users and lowest-cost logistics, Meesho is defending its value commerce crown against giants like Amazon and Flipkart.
-
High US Salaries, No Green Card Certainty: The Financial Calculation Facing Indian H-1B Families
The suspension of PERM processing at eight technology employers does not cancel existing H-1B visas. What it does is force a question many Indian families have been avoiding: is the US salary worth tying your career and family plans to one employer?
-
Swiggy vs Eternal: Food Delivery's Two Rivals Are No Longer In The Same Race
Eternal is building a private AI assistant, dark.ai. Swiggy is still working out how to make Instamart pay, with an operating loss of Rs 895 crore in the July-September quarter while Blinkit stayed profitable.
-
Where You Live Shapes How You Get To Work | The Reason Why
Two-wheelers are the most popular way to get to work in India, accounting for nearly 43% of workplace commutes.
-
Unhedged Position: Can India See An Indonesia-Style Time Correction?
The Nifty is trading below levels it first clocked in 2024. Is there, then, as I have suggested in the headline, potential that the current time correction drags on painfully for the next three-five, even ten years?