Canals with a cumulative length of nearly 5,700 kilometres are yet to be constructed as part of the Sardar Sarovar Narmada project, Chief Minister Bhupendra Patel told the Gujarat Assembly on Thursday.
Patel, who holds the Narmada portfolio, was replying to a written query by Congress MLA Geniben Thakor during Question Hour on the status of the Narmada project.
"Canals with a cumulative length of 5,724.41 km are yet to be built. Although the main canal has been completed, 0.64 km of branch canals, 157.39 km of distributaries, 1,006.02 km of minor canals and 4,560.36 km of sub-minor canals are yet to be constructed as on December 31, 2023,' Patel said in his written reply.
In 2023, canals having cumulative length of 251.23 km were constructed, including 0.29 km of branch canals, 14.29 km of distributaries, 64.82 km of minor canals and 171.83 km of sub-minor canals, he added.
Pending works of minor canals would be completed at the earliest subject to land acquisition and grant of permissions by various departments since they pass through forests, sanctuaries and under utilities like oil pipelines and power lines, the CM informed the House.
Since sub-minor canals are constructed in partnership with farmers, pending works of these will be taken up in a phased manner after getting permission from farmers of the command area, the CM said.
RECOMMENDED FOR YOU

KPI Green Order Win: KP Group CMD Says Coming Quarters To See Very Good Installation Capacity


Japan's Ambassador, Minister Of Economic Development Meet Gujarat CM To Discuss Economic Ties


Stocks To Buy, Sell, Or Hold: Shrikant Chouhan's Insights On SBI, Lupin And Gujarat Narmada


Air India Plane Crash: Ahmedabad Airport Temporarily Shut — Read Official Statement